Latest update for £38m A46 Stoneleigh Island redevelopment

By James Smith 17th Oct 2021

Latest photos of the building site (Images via WCC)
Latest photos of the building site (Images via WCC)

The latest update on the £38 million A46 Stoneleigh Island works has been released by Warwickshire County Council.

Having started in December 2020, the works will continue until at least summer 2022 and will see a new roundabout, and bridge built at the site.

Since the last update the earthworks for the Northbound on slip have been completed and the foundations for the actual road are now underway.

As too are foundations for the southbound off slip.

A Vodaphone communications cable which runs along the A46 is having to be moved, so three-way off-peak traffic lights have been installed to allow the work to take place.

Construction of the new bridge has already begun. This will see 30 7.5m piles driven into the ground along Finham Brook to make the foundations.

WCC is also now predicting that the 50mph speed limit and narrow lanes around the junction will only be in place for six months.

Kerbing on the new slip roads is due to begin this month also.

Follow this link for more information on the £38 million redevelopment plans.

     

Please Donate Kenilworth. Your Town. Your News. Your Support Matters.

Local news is essential for our community — but it needs your support.
By becoming a monthly supporter, you’ll help us continue delivering reliable local stories and events.
Your support makes a real difference to Kenilworth.
Monthly supporters will enjoy:
Ad-free experience

Share:


Sign-up for our FREE newsletter...

We want to provide kenilworth with more and more clickbait-free news.

     

...or become a Supporter.
Kenilworth. Your Town. Your News.

Local news is essential for our community — but it needs your support.
Your donation makes a real difference.
For monthly donators:
Ad-free experience