New photos and update on HS2 works in Burton Green and Balsall Common
By Sam Greenway - Local Democracy Reporter
31st Oct 2024 1:00 pm | Local News
The latest pictures of the major construction projects for the building of HS2 in Solihull have been revealed.
Solihull Metropolitan Borough Council gave planning approval to HS2 Interchange Station in 2020. It will serve Solihull, Birmingham Airport and the NEC.
The plan is for the high-speed rail link – which will slash travel times between London and Birmingham – to open between 2029 and 2033.
At the latest meeting of the council's HS2 implementation advisory group Tahir Ahmed, senior engagement and interface manager at Balfour Beatty Vinci (BBV) – HS2's construction partner for the West Midlands – provided updates on various HS2 projects and provided new images.
Burton Green
Mr Ahmed said: "We are starting to dig under Cromwell Lane.
"The retaining structure we are working our way up to Waste Lane.
"We are making really good progress."
Balsall Common Viaduct
A number of cofferdams – an enclosure built within a body of water to allow the enclosed area to be pumped out or drained – are being constructed at this site.
He reported there were 16 piers to construct adding: "You will start seeing those come out of the ground in the next three to six months."
River Blythe Viaduct
The work here sees the construction of viaduct piers as cofferdams are in.
Mr Ahmed said there would be temporary traffic management installed to create a safe working area while work continues.
Lavender Hall Lane Overbridge
"The next phase of work is to install the beams and to complete the deck," the HS2 chief said.
"Once we have completed the structure, we will require a long-term closure of Lavender Hall Lane – 12 to 14 months – to complete the road realignment."
Waste Lane Overbridge
Mr Ahmed said over the next nine months work will be completed on this overbridge, with the aim to bring it into use by "late 2025, early 2026".
A452 Overbridge
The bridge is complete here.
Mr Ahmed said: "We will construct the new road and start work on the roundabout – that will require some traffic management on the A452."
Carol Green Overbridge
Providing an update on this project he said: "The next phase of works are to install the parapets and, going into next year, we will start the earthworks on the embankment."
A45 Overbridge
Two service bridges are to be completed.
"Once these service bridges are complete we will switch traffic from the existing road onto the new bridges," he said.
M42 Motorway Box
Mr Ahmed said teams were creating a "working area" either side of the motorway and central reservation.
"We have got some weekend closures coming up going into early December," he added.
The meeting was held at the Civic Suite on October 24.
New kenilworth Jobs Section Launched!!
Vacancies updated hourly!!
Click here: kenilworth jobs
Share: