New photos and update on HS2 works in Burton Green and Balsall Common

By Sam Greenway - Local Democracy Reporter

31st Oct 2024 | Local News

HS2 works around Waste Lane (image via HS2)
HS2 works around Waste Lane (image via HS2)

The latest pictures of the major construction projects for the building of HS2 in Solihull have been revealed. 

Solihull Metropolitan Borough Council gave planning approval to HS2 Interchange Station in 2020. It will serve Solihull, Birmingham Airport and the NEC.

The plan is for the high-speed rail link – which will slash travel times between London and Birmingham – to open between 2029 and 2033.

At the latest meeting of the council's HS2 implementation advisory group Tahir Ahmed, senior engagement and interface manager at Balfour Beatty Vinci (BBV) – HS2's construction partner for the West Midlands – provided updates on various HS2 projects and provided new images.  

Burton Green

Mr Ahmed said: "We are starting to dig under Cromwell Lane. 

"The retaining structure we are working our way up to Waste Lane. 

"We are making really good progress." 

HS2 works at Cromwell Lane (Image via HS2)

Balsall Common Viaduct

A number of cofferdams – an enclosure built within a body of water to allow the enclosed area to be pumped out or drained – are being constructed at this site.

He reported there were 16 piers to construct adding: "You will start seeing those come out of the ground in the next three to six months."

Works around Balsall Common (Image via HS2)

River Blythe Viaduct

The work here sees the construction of viaduct piers as cofferdams are in.

Mr Ahmed said there would be temporary traffic management installed to create a safe working area while work continues. 

Lavender Hall Lane Overbridge

"The next phase of work is to install the beams and to complete the deck," the HS2 chief said.

"Once we have completed the structure, we will require a long-term closure of Lavender Hall Lane – 12 to 14 months – to complete the road realignment."

Waste Lane Overbridge

Mr Ahmed said over the next nine months work will be completed on this overbridge, with the aim to bring it into use by "late 2025, early 2026".

A452 Overbridge

The bridge is complete here. 

Mr Ahmed said: "We will construct the new road and start work on the roundabout – that will require some traffic management on the A452."

Carol Green Overbridge

Providing an update on this project he said: "The next phase of works are to install the parapets and, going into next year, we will start the earthworks on the embankment."

A45 Overbridge 

Two service bridges are to be completed. 

"Once these service bridges are complete we will switch traffic from the existing road onto the new bridges," he said.

Two bridges will be built around the A45 (image via HS2)

M42 Motorway Box

Mr Ahmed said teams were creating a "working area" either side of the motorway and central reservation. 

"We have got some weekend closures coming up going into early December," he added.

The meeting was held at the Civic Suite on October 24.

Closures are coming up around the M42 for HS2 works (image via HS2)

     

New kenilworth Jobs Section Launched!!
Vacancies updated hourly!!
Click here: kenilworth jobs

Share:

Related Articles

Most businesses don’t realise they are paying too much for their energy. Let the team at Radius Energy help you fix that (Nub News).
Advertisement Features

Kenilworth businesses: Save up to 50 per cent on your energy bills

W164 was significantly rerouted in March 2022 (image by Robin Stott)
Local News

New bridge will see diverted Kenilworth footpath taken over HS2 line

Sign-Up for our FREE Newsletter

We want to provide kenilworth with more and more clickbait-free local news.
To do that, we need a loyal newsletter following.
Help us survive and sign up to our FREE weekly newsletter.

Already subscribed? Thank you. Just press X or click here.
We won't pass your details on to anyone else.
By clicking the Subscribe button you agree to our Privacy Policy.