Councillors are calling for an external review after it emerged Warwick District Council lost almost £11 million on the sale of one of the ex-school sites primed for housing in Kenilworth.

The district paid £24.04 million for the Leyes Lane part of the former Kenilworth School in December 2020. Having taken on costly responsibilities for more than five years, it was then sold to Homes England for £13.097 million in March 2026.

The loss of £10.943 million does not account for any of the other costs associated with the security and maintenance of the site, nor does it include any losses on the other school site – Rouncil Lane – that it purchased but has yet to sell on.

A lessons learned review was presented to the council's overview and scrutiny committee this week in which global economic factors like Covid, the wars in Ukraine and the Middle East and the consequent effect on interest rates were cited.

However, the council strategic director David Elkington acknowledged that elected officials – the council was run by the Conservatives at the time of the purchase before the project was overseen by a Green-Labour administration from May 2023 – were not fully appraised of potential risks, partly because interest rates had been so low for so long.

Those low rates influenced the decision to pay slightly over market value for Leyes Lane with the council's primary focus on helping the school to relocate to a modernised site with greater capacity – and it is noted that more children are now attending the new school than could have been accommodated at the old site.

On top of that, the council's project management capacity at the time hampered its ability to be prepared for shocks, while the nature of the deal left the authority saddled with all of the financial risk.

Another flaw noted by Mr Elkington was that he had been unable to find information from project boards that the council was represented on with staff members from that time no longer with the district.

advertisement

Current portfolio holder for resources Cllr Jonathan Chilvers said: "I don't think we were appraised of the risk that quickly" after the change of power in 2023, while former cabinet member for housing Cllr Paul Wightman – now a member of the scrutiny panel – went further, stating that "none of the relevant information was shared" with councillors on the emerging risks for more than a year.

There were mixed feelings about what had transpired with Cllr Adrian Barton suggesting the council had been a "victim of forward thinking", ending up with its "toes and fingers burnt" for facilitating a much-needed project at a time when other bodies were unwilling to step in.

Liberal Democrat group leader Cllr Alan Boad later questioned whether the council had been suitably equipped to act without drafting in external expertise.

"The council has been badly burnt on this," he said.

"It has been outplayed by the team that was doing the schools, they spotted where they could get through an avenue and they were in.

"Lots of debate went on but who picked up all the risk? The council. How the hell did we get in that position? We should never have done it.

"If we want to do this kind of work, we need a team that is capable of doing it."

Mr Elkington later detailed how such proposals are no longer progressed without delivery and resourcing plans and that the council now has far greater project management capacity. He said more extensive risk profiles are now offered to councillors when signing off decisions too.

advertisement

"There are things working much better now than they used to," he said.

Nevertheless, the scrutiny panel voted six-four in favour of asking the cabinet – now solely run by the Green Party – to commission an external review of whether the new safeguards are adequate, while the Liberal Democrat opposition wants independent oversight of historic failings.

In a statement, scrutiny panel member Cllr Richard Dickson said: "The new Kenilworth school is a vital asset but councillors have known for some time that Warwick District Council lost a lot of money on the former school sites.

"Until now we have been unable to say anything publicly as it has been shrouded in secrecy so we welcome the work that officers have done to make some of the facts and figures public, and to start the process of learning lessons.

"However, we still don't know what the total impact to the council's finances will be. Also still unclear is the extent to which the previous Conservative administration overpaid for the sites, whether the Green Party-Labour coalition racked up additional needless losses on the sites or whether the council has been a helpless victim of circumstance.

"We will continue to press the current Green administration to make all of the relevant facts and figures public, and to commission an external review of this disastrous set of losses."

Download our Nub News App: - It’s FREE and available now
- Breaking news notifications
- Your Town in Your Pocket

     

Local news is in crisis.

Newspapers around the country are closing at an alarming rate.

Nub News is changing that.
Please consider supporting us.
Your contribution will be a GAME-CHANGER.
Monthly supporters will enjoy:
Ad-free experience
advertisement

Share:

Comments (0)

Post comment

No comments yet!


advertisement

Downdload our Nub News App:
- It’s FREE and available now
- Breaking news notifications
- Your Town in Your Pocket